BEYOND is a church-wide journey we started Spring 2024 where we will grow our relationship with God, build our faith and look beyond where we are to where God is calling us to go. 

LeaderVisionNight_Slides_Background_1920x1080.jpg
  • Build a New Worship Center

  • Expand the Next Gen Space

  • Expand the Lobby & Outdoor Gathering Space

*renderings subject to change

 

Pray

Be A Vision Carrier

Give As God Leads You

With a total project cost of $20-24M, we have a pledge goal of $15M.

 

Construction is underway on the Next Gen Phase, costing $3.6M, with completion expected by summer of 2026. This phase will be paid for in cash with funds given to Beyond, as well as all current debt is expected to be paid (currently ~$2.3M), meaning that by the summer of 2026, we expect to be fully debt free with the Next Gen Phase completed. We will begin the new worship center phase when the appropriate financing threshold is reached, including receiving the necessary amount of funds on hand.